Fiscal Note
The proposed resolution approves plan documents for the reconstruction of North Blair Street at a total estimated cost of $1,600,000. The adopted 2017 budget for Engineering-Major Streets contains the project's budget authority within the Reconstruction Streets capital program (MUNIS 11470), which was added to the program budget in 2017 via adoption of resolution #46519. Project costs will be assigned to associated agencies as follows:
Major Streets - $940,000
Sewer Utility - $360,000
Water Utility - $300,000
Title
Approving Plans, Specifications, And Schedule Of Assessments For North Blair Street Reconstruction Assessment District - 2017.
Body
The Board of Public Works and the City Engineer having made reports of all proceedings in relation to the improvement of North Blair Street Reconstruction Assessment District - 2017 pursuant to a resolution of the Common Council, RES-17-00498, ID No. 47514, adopted June 20, 2017, which resolution was adopted thereto, and the provisions of the Madison General Ordinances and the Wisconsin Statutes in such case made and provided, and the Common Council being fully advised.
BE IT RESOLVED:
1. That the City at large is justly chargeable with and shall pay the sum o $1,485,000.00 of the entire cost of said improvement.
2. That for those eligible property owners requesting construction of a rain garden in the public right-of-way adjacent to their property shall execute the necessary waiver of special assessments on forms provided by the City Engineer;
3. That the sum assigned to each separate parcel, as indicated on the attached schedule of assessment, is hereby specially assessed upon each such parcel.
4. That the Common Council determines such special assessments to be reasonable.
5. That the work or improvement be carried out in accordance with the reports as finally approved.
6. That such work or improvement represents an exercise of the police power of the City of Madison.
7. That the plans & specific...