Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53B0691 $392,331.23
Acc't. No. CS53-58270-810355-00-53B0691 $45,450.87
Acc't. No. ESTM-58270-810381-00-53B0691 $169,613.38
Acc't. No. ES01-58275-810332-00-53B0691 $408,045.02
Acc't. No. EW01-58273-810455-00-53B0691 $366,648.71
Title
Improvements accepted for Chandler St., S. Charter St., & Orchard St. Reconstruction Assessment District - 2007, Contract No. 5931.
Body
BE IT RESOLVED, that the improvements on Chandler St., S. Charter St. & Orchard St. Reconstruction Assessment District - 2007 have been completed on 8/16/08 be and are hereby accepted.
Original Contract Sum $ 1,567,736.58
(Based on Actual Units) $ 1,381,638.61
Net Change by Change Orders $ 2,430.60 or 0.16%
Liquidated Damages $ 1,980.00
Final Contract Amount $ 1,382,089.21