File #: 18131    Version: 1 Name: Improvements accepted for Annual Sawcutting of Concrete Sidewalk & Incidental Work, Contract No. 6294.
Type: Resolution Status: Passed
File created: 4/13/2010 In control: BOARD OF PUBLIC WORKS
On agenda: 5/4/2010 Final action: 5/4/2010
Enactment date: 5/5/2010 Enactment #: RES-10-00421
Title: Improvements accepted for Annual Sawcutting of Concrete Sidewalk & Incidental Work, Contract No. 6294.
Sponsors: BOARD OF PUBLIC WORKS

Title

Improvements accepted for Annual Sawcutting of Concrete Sidewalk & Incidental Work, Contract No. 6294.

Body

BE IT RESOLVED, that the improvements on Annual Sawcutting of Concrete Sidewalk & Incidental Work have been completed on 11/30/09 be and are hereby accepted. 

 

Original Contract Sum                     $          204,025.00

(Based on Actual Units)                     $         219,978.95

Net Change by Change Orders                     $                   0.00 or 0.00%

Liquidated Damages                     $                   0.00

Final Contract Amount                     $         219,978.95

Fiscal Note

Breakdown of Costs by Account Number:

 

Acc’t. No. CS53-54473-810376-00-53W0707           $219,978.95