Fiscal Note
The proposed resolution awards the contract for the flood mitigation at Hawks Landing for a total cost of $1,149,740. Funding is provided by Stormwater Utility funded GO Borrowing via the Citywide Flood Mitigation program authorized within the adopted 2019 capital budget for the Stormwater Utility.
MUNIS:
11857
Title
Awarding Public Works Contract No. 8421, Hawks Landing Flood Mitigation South - 2019. (1st AD)
Body
BE IT RESOLVED, that the following low bids for miscellaneous improvements be accepted and that the Mayor and City Clerk be and are hereby authorized and directed to enter into a contract with the low bidder contained herein, subject to the Contractor's compliance with Section 39.02 of the Madison General Ordinances concerning compliance with the Affirmative Action provisions and subject to the Contractor's compliance with Section 33.07 of the Madison General Ordinances regarding Best Value Contracting:
BE IT FURTHER RESOLVED, that the funds be encumbered to cover the cost of the projects contained herein.
See attached document (Contract No. 8421) for itemization of bids.