Fiscal Note
This resolution increases the Total Plant Value for the Madison Storm Water Utility $73,603.97.
Title
Accepting detention basin improvements constructed by private contract in Hawks Creek, Private Contract No. 2105. (1st AD)
Body
WHEREAS, Badger Mill Creek, LLC, has satisfactorily completed the installation of detention basin improvements by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Hawks Creek
NOW, THEREFORE, BE IT RESOLVED, that said detention basin improvements be and are hereby accepted.
BE IT FURTHER RESOLVED, that said detention basin improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service."
Increase in Total Plant Value per Schedule "A" $73,603.97