Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53B0876 $293,325.93
Acc't. No. ESTM-58270-810381-00-53B0878 $105,165.00
Acc't. No. ES01-58275-810332-00-53B0876 $156,193.63
Acc't. No. EW01-58273-810455-00-53B0876 (#7205) $156,790.50
Title
Improvements accepted for Bashford Avenue, Ohio Avenue Reconstruction Assessment District - 2004, Contract No. 5579. (6th AD)
Body
BE IT RESOLVED, that the storm sewer, sanitary sewer, street and water main improvements on Bashford Avenue, Ohio Avenue Reconstruction Assessment District - 2004 have been completed on 6/11/05 be and are hereby accepted.
Original Contract Sum $ 714,642.62
(Based on Actual Units) $ 700,726.06
Net Change by Change Orders $ 11,749.00 or 1.64%
Liquidated Damages $ 0.00
Final Contract Amount $ 712,475.06