Title
Improvements accepted for Chip Sealing 2007 - District 7, Contract No. 6010.
Body
BE IT RESOLVED, that the improvements on Lien Road Partial Reconstruction - Sidewalk Fill @ Autumn Woods III have been completed on 5/19/07 be and are hereby accepted.
Original Contract Sum $ 108,905.01
(Based on Actual Units) $ 108,905.01
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 0.00
Final Contract Amount $ 108,905.01
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810366-00-5B0999 $108,905.01