Legislation Details

File #: 93014    Version: 1 Name: Review Future Change Order for the State Street Campus Garage Project.
Type: Miscellaneous Status: In Committee
File created: 5/4/2026 In control: BOARD OF PUBLIC WORKS
On agenda: Final action:
Enactment date: Enactment #:
Title: Review Future Change Order for the State Street Campus Garage Project.
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
No records to display.

Title

Review Future Change Order for the State Street Campus Garage Project.

Body

City Engineering to present on an expected future change order for the State Street Campus Garage project.  Change Order submitted to the City is $50,315.02, but still under review.  The Contractor is indicating that a remote fill station and additional venting not shown on the Contract Drawings is required at the diesel generator serving the Garage and Housing.