Title
Review Future Change Order for the State Street Campus Garage Project.
Body
City Engineering to present on an expected future change order for the State Street Campus Garage project. Change Order submitted to the City is $50,315.02, but still under review. The Contractor is indicating that a remote fill station and additional venting not shown on the Contract Drawings is required at the diesel generator serving the Garage and Housing.