Madison, WI Header
File #: 09048    Version: 1 Name: Change Order No. 3 to Contract No. 5999, Park Street Reconstruction and Construction of Relief Storm Sewer, to Speedway Sand & Gravel, in the amount of $3,841.90.
Type: Miscellaneous Status: Approved
File created: 1/31/2008 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 2/20/2008
Enactment date: Enactment #:
Title: Change Order No. 3 to Contract No. 5999, Park Street Reconstruction and Construction of Relief Storm Sewer, to Speedway Sand & Gravel, in the amount of $3,841.90.
Attachments: 1. co 3 - 5999.pdf

Title

Change Order No. 3 to Contract No. 5999, Park Street Reconstruction and Construction of Relief Storm Sewer, to Speedway Sand & Gravel, in the amount of $3,841.90. 

Body

See attached.