Title
Improvements accepted for Annual Construction & Reconstruction of Concrete & Incidental Concrete Curb & Gutter Work Ordered (District 6) by the Common Council, Contract No. 5904.
Body
BE IT RESOLVED, that the improvements on Annual Construction & Reconstruction of Concrete & Incidental Concrete Curb & Gutter Work Ordered (District 6) by the Common Council have been completed on 11/17/07 be and are hereby accepted.
Original Contract Sum $ 654,125.00
(Based on Actual Units) $ 437,889.62
Net Change by Change Orders $ 6,675.63 or 1.02%
Liquidated Damages $ 0.00
Final Contract Amount $ 444,565.25
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58280-810376-00-53W0318 $444,565.25