Fiscal Note
Breakdown of costs by account numbers: Acc't. No. CS53-58250-810041-00-53B0847 $92,536.26 and Acc't. No. CW53-58270-810079-00-53B0847 $82,311.73
Title
Improvements accepted for Sutherland Court Reconstruction Assessment District - 2003 Contract No. 5400 (6th AD)
Body
BE IT RESOLVED, that the street and storm sewer improvements on Sutherland Court Reconstruction Assessment District - 2003 have been completed on 11/28/03 be and are hereby accepted.
Original Contract Sum $174,039.00
(Based on Actual Units) $170,347.99
Net Change by Change Orders $4,500.00 or 2.59%
Liquidated Damages $0.00
Final Contract Amount $174,847.99