Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CL53-54810-810351-00-53B0942
$3,925,304.65
Title
Improvements accepted for Olin Landfill Remediation - Phase II Remedial Action Construction, Contract No. 5447.
Body
BE IT RESOLVED, that the landfill improvements on Olin Landfill Remediation - Phase II Remedial Action Construction have been completed on 5/17/04 be and are hereby accepted.
Original Contract Sum $ 2,936,855.20
(Based on Actual Units) $ 3,762,590.89
Net Change by Change Orders $ 168,969.05 or 5.75%
Liquidated Damages $ 48,591.29
Final Contract Amount $ 3,925,304.65