Madison, WI Header
File #: 00531    Version: 1 Name: Improvements accepted for Olin Landfill Remediation - Phase II Remedial Action Construction, Contract No. 5447
Type: Resolution Status: Passed
File created: 2/9/2005 In control: BOARD OF PUBLIC WORKS
On agenda: 3/1/2005 Final action: 3/1/2005
Enactment date: 3/4/2005 Enactment #: RES-05-00204
Title: Improvements accepted for Olin Landfill Remediation - Phase II Remedial Action Construction, Contract No. 5447.
Sponsors: Common Council By Request

Fiscal Note

Breakdown of Costs by Account Number:

Acc't. No. CL53-54810-810351-00-53B0942

  $3,925,304.65

 

Title

Improvements accepted for Olin Landfill Remediation - Phase II Remedial Action Construction, Contract No. 5447.

 

Body

BE IT RESOLVED, that the  landfill   improvements on Olin Landfill Remediation - Phase II Remedial Action Construction     have been completed on 5/17/04  be and are hereby accepted. 

 

Original Contract Sum                    $      2,936,855.20

(Based on Actual Units)                 $      3,762,590.89

Net Change by Change Orders       $         168,969.05 or 5.75%

Liquidated Damages                      $           48,591.29

Final Contract Amount                   $      3,925,304.65