Skip to main content
Madison, WI Header
File #: 89938    Version: 1 Name: Accepting stormwater management improvements constructed by Private Contract In Sugar Maple – Phase 1, Private Contract No. 2317.
Type: Resolution Status: Passed
File created: 9/10/2025 In control: Engineering Division
On agenda: 10/7/2025 Final action: 10/7/2025
Enactment date: 10/10/2025 Enactment #: RES-25-00523
Title: Accepting stormwater management improvements constructed by Private Contract In Sugar Maple – Phase 1, Private Contract No. 2317 (District 1).
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2317 Pond Greenway Schedule A.pdf

Fiscal Note

No City Funds required. Private contract.

Title

Accepting stormwater management improvements constructed by Private Contract In Sugar Maple – Phase 1, Private Contract No. 2317 (District 1).

Body

WHEREAS, Sugar Maple Madison, LLC, has satisfactorily completed the installation of stormwater management improvements by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in:  Sugar Maple – Phase 1.

 

 

NOW, THEREFORE, BE IT RESOLVED

 

1.  That said stormwater management improvements be and are hereby accepted. 

 

2. That said stormwater management improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service". 

 

 

Increase in Total Plant Value per Schedule “A”                     $318,396.59.