Title
Improvements accepted for Hoard Street, Upham Street & Seventh Street Reconstruction Street Assessment District - 2006, Contract No. 5936. (12th AD)
Body
BE IT RESOLVED, that the street, water main, and storm and sanitary sewer improvements on Hoard Street, Upham Street & Seventh Street Reconstruction Street Assessment District - 2006 have been completed on 11/30/06 be and are hereby accepted.
Original Contract Sum $ 1,023,191.65
(Based on Actual Units) $ 944,539.16
Net Change by Change Orders $ 1,915.80 or 0.18%
Liquidated Damages $ 0.00
Final Contract Amount $ 946,454.96
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53W0337 $284,493.06
Acc't. No. CS53-58270-810355-00-53W0337 $26,752.50
Acc't. No. ESTM-58270-810381-00-53W0337 $83,972.00
Acc't. No. ES01-58275-810332-00-53W0337 $258,188.95
Acc't. No. EW01-58273-810455-00-53W0337 $293,048.45