Madison, WI Header
File #: 85615    Version: 1 Name: Change Order No. 2 to Contract 8717, East-West Bus Rapid Transit Widened Sidewalk, to Parisi Construction for $204,243.05 and an additional 91 days.
Type: Miscellaneous Status: Approved
File created: 10/8/2024 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 10/9/2024
Enactment date: Enactment #:
Title: Change Order No. 2 to Contract 8717, East-West Bus Rapid Transit Widened Sidewalk, to Parisi Construction for $204,243.05 and an additional 91 days. (District 9, District 11, District 19)
Attachments: 1. 8717 Change order 2.pdf

Title

Change Order No. 2 to Contract 8717, East-West Bus Rapid Transit Widened Sidewalk, to Parisi Construction for $204,243.05 and an additional 91 days. (District 9, District 11, District 19)

Body

See Attached.