Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53W0758 $158,022.15
Acc't. No. CS53-58270-810355-00-53W0758 $7,365.44
Acc't. No. ESTM-58270-810381-00-53W0758 $7,208.62
Acc't. No. ES01-58275-810332-00-53W0758 $98,096.67
Acc't. No. EW01-58273-810455-00-53W0758 $112,644.66
Title
Improvements accepted for Terry Place Reconstruction Assessment District - 2009, Contract No. 6299.
Body
BE IT RESOLVED, that the improvements on Terry Place Reconstruction Assessment District - 2009 have been completed on 11/10/09 be and are hereby accepted.
Original Contract Sum $ 433,756.40
(Based on Actual Units) $ 386,697.54
Net Change by Change Orders $ 0.00 or 0.00%
Liquidated Damages $ 3,360.00
Final Contract Amount $ 383,337.54