Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on Schroeder Road and Whitney Way.
Body
PREAMBLE
The 2012 Phase 1 contract for cured-in-place rehabilitation includes the lining of approximately 22,990 linear feet of sanitary sewer mains. The contractor performing this work has requested permission to perform the work required to line one segment of sanitary sewer main in Schroeder Road and Whitney way outside the hours of 7:00 AM to 7:00 PM to begin no earlier than Monday, January 28th, 2013 and complete no later than Friday, February 8th, 2013. The total length of this sanitary sewer main is 270 linear feet.
Madison General Ordinance section 24.08(3) provides the Common Council the ability to allow construction activities outside of the hours of 7:00 AM to 7:00 PM with the passage of a resolution and a hearing before the Board of Public Works. The contractor performing this work has requested permission to perform the work required to line the one segment of sanitary sewer main in Schroeder Road and Whitney Way outside the hours of 7:00 AM to 7:00 PM because:
1. The section of sanitary sewer main to be lined has high flow during the hours of 7:00 AM to 7:00 PM.
2. The streets where this work is scheduled to occur convey high volumes of traffic. Activities associated with lining these sanitary mains will disrupt live traffic causing considerable disruption and delay.
The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:
1. Hydraulic cleaning of the sanitary sewer main sections to be lined to remove any accumulated debris prior to lining;
2. Conducting a closed-circuit inspection of the sanitary sewer mains to be lined to confirm that the line has been adequately cleaned prior to lining and to provide documentation to the City of pre-lining. conditions;
3. Installing the resin-impregnated felt liner into the sanitary sewer main;
4....