Madison, WI Header
File #: 52516    Version: 1 Name: Assessing Benefits - Capital Square Pavement Replacement Phase 2.
Type: Resolution Status: Passed
File created: 7/17/2018 In control: BOARD OF PUBLIC WORKS
On agenda: 8/7/2018 Final action: 8/7/2018
Enactment date: 8/10/2018 Enactment #: RES-18-00599
Title: Assessing Benefits - Capital Square Pavement Replacement Phase 2. (4th AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 12 S. Carroll Street Sewer Lateral.pdf, 2. 22 S Carroll Street sidewalk.pdf, 3. 11429FINAL_Main_Carroll_Pinckney_Assess.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
8/7/20181 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25Pass Action details Meeting details Not available
7/25/20181 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
7/18/20181 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

No Appropriation Required.

Title

Assessing Benefits - Capital Square Pavement Replacement Phase 2. (4th AD)

Body

WHEREAS, the construction of improvement(s) on Capital Square Pavement Replacement Phase 2 has been completed; and,

 

WHEREAS, it has been determined that the abutting property is to pay the amount per the attached schedule of assessments.

 

NOW, THEREFORE, BE IT RESOLVED, that the sums so charged to the abutting property be and are hereby assessed and levied upon said property payable by the owners of the lots or parcels of land benefited as determined by the Board of Public Works, and in accordance with its recommendations, the amount so charged to each of the lots or parcels of land so benefited being as follows, to wit: