Madison, WI Header
File #: 74551    Version: 1 Name: Accepting detention and infiltration basin constructed by Private Contract Linden Park - Phase 10, Private Contract No. 2311.
Type: Resolution Status: Passed
File created: 11/4/2022 In control: Engineering Division
On agenda: 12/6/2022 Final action: 12/6/2022
Enactment date: 12/9/2022 Enactment #: RES-22-00797
Title: Accepting detention and infiltration basin constructed by Private Contract Linden Park - Phase 10, Private Contract No. 2311. (1st AD)
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 53B2311 Linden Park Ph 10 POND Schedule A Unit Cost.pdf

Fiscal Note

No City Funds required. Private contract.

Title

Accepting detention and infiltration basin constructed by Private Contract Linden Park - Phase 10, Private Contract No. 2311. (1st AD)

Body

WHEREAS, Veridian Homes AB, LLC, has satisfactorily completed the installation of a detention and infiltration basin, by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in:  Linden Park - Phase 10.

 

 

NOW, THEREFORE, BE IT RESOLVED

 

1.  That said detention and infiltration be and are hereby accepted. 

 

2. That said detention and infiltration basin improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule “A” representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility’s “Utility Plant in Service”.

 

Increase in Total Plant Value per Schedule “A”                      $33,979.00