File #: 14754    Version: 1 Name: Improvements accepted for West Beltline Frontage Road/Todd Drive Reconstruction, Contract No. 5900
Type: Resolution Status: Passed
File created: 5/13/2009 In control: BOARD OF PUBLIC WORKS
On agenda: 6/2/2009 Final action: 6/2/2009
Enactment date: 6/5/2009 Enactment #: RES-09-00543
Title: Improvements accepted for West Beltline Frontage Road/Todd Drive Reconstruction, Contract No. 5900.
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number.  ES01-58275-810332-00-53W0303 - $220,510.55
Title
Improvements accepted for West Beltline Frontage Road/Todd Drive Reconstruction, Contract No. 5900.
Body
BE IT RESOLVED, that the improvements on West Beltline Frontage Road/Todd Drive Reconstruction have been completed on 1/9/07 and are hereby accepted.
 
Original Contract Sum            $      211,125.60
(Based on Actual Units)            $      210,194.84
Net Change by Change Orders      $      10,315.71 or 4.88%
Liquidated Damages                  $                 0.00
Final Contract Amount            $      220,510.55