Title
Improvements accepted for S. High Point Road Reconstruction Assessment District - 2006 (Incl. District 2 - 2006), Contract No. 5935.
Body
BE IT RESOLVED, that the improvements on S. High Point Road Reconstruction Assessment District - 2006 (Incl. District 2 - 2006) have been completed on 9/19/07 be and are hereby accepted.
Original Contract Sum $ 989,057.50
(Based on Actual Units) $ 976,663.56
Net Change by Change Orders $ 152,993.61 or 15.47%
Liquidated Damages $ 0.00
Final Contract Amount $ 1,129,657.17
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810364-00-53W0256 $749,326.64
Acc't. No. CS53-58270-810364-00-53W0256 $45,292.50
Acc't. No. ESTM-58270-810381-00-53W0256 $122,437.45
Acc't. No. ES01-58275-810335-00-53W0256 $104,564.70
Acc't. No. CS53-58545-810364-00-53W0256 $24,146.50
Acc't. No. CS53-58540-810364-00-53W0256 $14,235.38
Acc't. No. EW01-58273-810455-00-53W0256 $69,654.00