Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53W0434-53TIF037 $235,836.45
Acc't. No. CS53-58270-810355-00-53W0434-53TIF037 $46,845.02
Acc't. No. ESTM-58270-810381-00-53W0434-53TIF037 $281,481.57
Acc't. No. ES01-58275-810332-00-53W0434 $85,096.30
Acc't. No. EW01-58273-810455-00-53W0434 $172,363.17
Title
Improvements accepted for Waubesa Street Reconstruction District 2008, Contract No. 6088.
Body
BE IT RESOLVED, that the improvements on Waubesa Street Reconstruction District 2008 have been completed on 9/22/08 be and are hereby accepted.
Original Contract Sum $ 822,826.60
(Based on Actual Units) $ 804,705.01
Net Change by Change Orders $ 24,897.50 or 3.03%
Liquidated Damages $ 7,980.00
Final Contract Amount $ 821,622.51