Title
Improvements accepted for Jean St. & Leitch Ct. Reconstruction Assessment District - 2008; North Pinckney St. Reconstruction Assessment District - 2008, Contract No. 6128.
Body
BE IT RESOLVED, that the improvements on Jean St. & Leitch Ct. Reconstruction Assessment District - 2008; North Pinckney St. Reconstruction Assessment District - 2008 have been completed on 10/30/08 be and are hereby accepted.
Original Contract Sum $ 739,014.40
(Based on Actual Units) $ 688,227.34
Net Change by Change Orders $ 6,047.20 or 0.82%
Liquidated Damages $ 7,980.00
Final Contract Amount $ 686,294.54
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810355-00-53W0020 $143,011.31
Acc't. No. CS53-58250-810355-00-53W0559 $80,512.22
Acc't. No. CS53-58270-810355-00-53W0020 $29,037.81
Acc't. No. CS53-58270-810355-00-53W0559 $15,635.74
Acc't. No. ESTM-58270-810381-00-53W0020 $77,048.09
Acc't. No. ESTM-58270-810381-00-53W0559 $9,522.80
Acc't. No. ES01-58275-810332-00-53W0020 $106,413.30
Acc't. No. ES01-58275-810332-00-53W0559 $47,156.04
Acc't. No. EW01-58273-810455-00-53W0020 $99,823.90
Acc't. No. EW01-58273-810455-00-53W0559 $57,300.07
Acc't. No. CS53-58545-810355-00-53W0559 $20,833.26