Skip to main content
Madison, WI Header
File #: 91628    Version: 1 Name: Change Order No. 5 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co Inc, for $0 and an additional 60 days for a completion date of 3/1/26.
Type: Miscellaneous Status: In Committee
File created: 1/21/2026 In control: BOARD OF PUBLIC WORKS
On agenda: Final action:
Enactment date: Enactment #:
Title: Change Order No. 5 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co Inc, for $0 and an additional 60 days for a completion date of 3/1/26. (District 12).
Attachments: 1. 9342 CO 5.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
No records to display.

Title

Change Order No. 5 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co Inc, for $0 and an additional 60 days for a completion date of 3/1/26. (District 12).

Body

See attached.