Title
Improvements accepted for Woodrow Street & Edgewood Drive Cul De Sac, Contract No. 5967. (10th AD)
Body
BE IT RESOLVED, that the improvements on Woodrow Street & Edgewood Drive Cul De Sac have been completed on 10/30/06 be and are hereby accepted.
Original Contract Sum $ 86,545.63
(Based on Actual Units) $ 79,457.62
Net Change by Change Orders $ 13,083.13 or 15.11%
Liquidated Damages $ 0.00
Final Contract Amount $ 92,540.75
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810360-00-53W0349 $79,042.75
Acc't. No. CS53-58270-810360-00-53W0349 $13,498.00