File #: 77142    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contracts In Chapel View – Surface Paving and Chapel View – Phase 2, Private Contract Nos. 8262 and 8263.
Type: Resolution Status: Passed
File created: 4/6/2023 In control: Engineering Division
On agenda: 5/2/2023 Final action: 5/2/2023
Enactment date: 5/8/2023 Enactment #: RES-23-00345
Title: Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contracts In Chapel View - Surface Paving and Chapel View - Phase 2, Private Contract Nos. 8262 and 8263 (9th AD).
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 8263 Chapel View Ph 2 Sanitary Schedule A Unit Cost UPDATED Mar2023.pdf, 2. 8263 Chapel View Ph 2 Storm Schedule A Unit Cost UPDATED Mar2023.pdf, 3. 8262 8263 Street Schedule A including bituminous.pdf
Fiscal Note
No City Funds required. Private contract.
Title
Accepting sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) constructed by Private Contracts In Chapel View - Surface Paving and Chapel View - Phase 2, Private Contract Nos. 8262 and 8263 (9th AD).
Body
WHEREAS, Chapel View Development Company, Inc., has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Chapel View - Surface Paving and Chapel View - Phase 2.


NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, and street improvements (including bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 109,278.52

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 109,278.52
b) Sewer Laterals $ ____-0-

C) Investments in Capital (MSU Share) $ ____-0-

D) Total Plant Value $ 109,278.52

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".


Increase in Total Plant Value per Schedule “A” $282,732.02.


4. That the street improvements, including the bituminous pavement, on the following streets be and are hereby accepted: