File #: 93659    Version: 1 Name: Change Order No. 7 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co., Inc., for $271,561.06 (over contingency), and 213 additional days.
Type: Miscellaneous Status: In Committee
File created: 6/17/2026 In control: BOARD OF PUBLIC WORKS
On agenda: Final action:
Enactment date: Enactment #:
Title: Change Order No. 7 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co., Inc., for $271,561.06 (over contingency), and 213 additional days (District 12).
Attachments: 1. 9342 Change Order 7.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
No records to display.

Title

Change Order No. 7 to Contract 9342, Well 15 PFAS Treatment Facility, to Joe Daniels Construction Co., Inc., for $271,561.06 (over contingency), and 213 additional days (District 12).

Body

See Attached.