Fiscal Note
In the adopted 2016 capital budget Engineering-Major Streets has budgeted $4.027 million in the Rural to Urban Streets program (MUNIS 10204) for the reconstrucion of streets with substandard pavement rating. The minor project for Park Frontage reimbursements for private development projects is established with sufficient funding for the work specified in the proposed resolution. Funding is from GO borrowing and the costs are reimbursable to the city via the private developer.
The proposed resolution approves plan documents at an estimated cost not to exceed $25,000.
MUNIS:
11125-402-170: 54410 (96339)
Title
Approving plans and specifications for public improvements required to serve Phase 4 of the Subdivision known as North Addition to Grandview Commons and authorizing construction to be undertaken by the Developer, Private Contract No. 7808. (3rd AD)
Body
WHEREAS, the developer, MREC VH Grandview Commons LLC, has received the City of Madison's approval to create the subdivision known as North Addition to Grandview Commons; and,
WHEREAS, Section 16.23(9) of the Madison General Ordinances requires the developer to install the public improvements necessary to serve the subdivision; and,
WHEREAS, Section 16.23(9) of the Madison General Ordinances allows the developer to install the improvements in construction phases provided that a Declaration of Conditions, Covenants, and Restrictions is executed for those lots included in future construction phases until such time as surety is provided to the City to guarantee the installation of the public improvements to serve said lots; and,
WHEREAS, the developer proposes to provide public improvements to serve Lots 846-850, 861-865, 880-881, 893-899, 903-908, 924-929, 986-990, OL 42, and OL 43 as Phase 4.
NOW, THEREFORE, BE IT RESOLVED:
1. That the Mayor and City Clerk are hereby authorized and directed to execute a Contract For the Construction of Public Improvements That Will be Accepted by the Ci...