File #: 09818    Version: 1 Name: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 20) by the Common Council, Contract No. 5821.
Type: Resolution Status: Passed
File created: 4/1/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 5/6/2008 Final action: 5/6/2008
Enactment date: 5/9/2008 Enactment #: RES-08-00475
Title: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 20) by the Common Council, Contract No. 5821. (20th AD)
Sponsors: BOARD OF PUBLIC WORKS
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 20) by the Common Council, Contract No. 5821.  (20th AD)
Body
BE IT RESOLVED, that the sidewalk improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (District 20) by the Common Council have been completed on 11/12/05 be and are hereby accepted.  
 
Original Contract Sum      $         462,120.00
(Based on Actual Units)      $         359,353.46
Net Change by Change Orders      $                   0.00 or 0.00%
Liquidated Damages      $                    0.00
Final Contract Amount      $         359,353.46
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58280-810376-00-53W0215     $462,120.00