Fiscal Note
Breakdown of costs by Acct. Nos.:
CS53-58260-810044-00-53B0868 $644,082.38
CT24-58250-822401-00-53B0727 $6,750.68
ES01-58272-810054-00-53B0868 $6,556.68
GN01-15640-000000-00-53B0868 $5,664.28
Title
Improvements accepted for Far East Bituminous Paving, and Bituminous Base Patching and Base Patch Grinding, Contract No. 5386. (Various ADs)
Body
BE IT RESOLVED, that the street, water main, and sanitary sewer improvements on Far East Bituminous Paving, and Bituminous Base Patching and Base Patch Grinding have been completed on 6/28/03 be and are hereby accepted.
Original Contract Sum $648,680.78
(Based on Actual Units) $626,440.14
Net Change by Change Orders $36,613.88 or 5.64%
Liquidated Damages $0.00
Final Contract Amount $663,054.02