Title
Improvements accepted for Edgewood Ave. Reconstruction Assessment District - 2010, Contract No. 6270.
Body
BE IT RESOLVED, that the improvements on Edgewood Ave. Reconstruction Assessment District - 2010 have been completed on 11/13/10 be and are hereby accepted.
Original Contract Sum $ 558,265.85
(Based on Actual Units) $ 545,102.70
Net Change by Change Orders $ 55,215.70 or 9.89%
Liquidated Damages $ 0.00
Final Contract Amount $ 600,318.40