Title
Improvements accepted for Westmorland Park Greenway, Contract No. 6040. (11th AD)
Body
BE IT RESOLVED, that the storm sewer improvements on Westmorland Park Greenway have been completed on 12/8/07 be and are hereby accepted.
Original Contract Sum $ 118,819.80
(Based on Actual Units) $ 114,853.89
Net Change by Change Orders $ 25,550.00 or 21.50%
Liquidated Damages $ 0.00
Final Contract Amount $ 140,403.89
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. ESTM-58270-810382-00-53B0959 $140,403.89