Fiscal Note
CL60-58201-810625-00-53W0853-00000000-00000000
The 2012 Adopted Capital Budget and the 2013 Executive Capital Budget as Recommended by the Board of Estimates include funding for the construction of phases IA and IB of the Central Park project (Pr. #23 Parks Division, Acct#810625). This contract is for phase IA. The City's funding for construction includes Park Impact Fees and G.O. Debt.
Estimated Construction Cost:
Total Project Cost: $ 3,225,200
State/Federal Cost $ 1,549,300
City Cost $ 1,675,900
Title
Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for Central Park - Phase IA. (6th AD)
Body
BE IT RESOLVED,
1. That the plans and specifications for Central Park - Phase 1A, be and are hereby approved
2. That the Board of Public Works be and is hereby authorized to advertise and receive bids for said project.
3. That the Mayor and City Clerk are hereby authorized to sign and grant easements or right-of-way release or procurement documents, maintenance agreements or encroachment agreements, as necessary and grant or accept dedication of lands and/or easements from/to the Developer/Owner for public improvements located outside of existing public fee title or easement right-of-ways.