File #: 09101    Version: 1 Name: Improvements accepted for Mineral Point Rd. @ Junction Rd. - Right Turn Lane, Contract No. 5966.
Type: Resolution Status: Passed
File created: 2/5/2008 In control: BOARD OF PUBLIC WORKS
On agenda: 3/4/2008 Final action: 3/4/2008
Enactment date: 3/6/2008 Enactment #: RES-08-00242
Title: Improvements accepted for Mineral Point Rd. @ Junction Rd. - Right Turn Lane, Contract No. 5966. (9th AD)
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number:
Acc't. No. CS53-58250-810359-00-53W0379                 $96,966.56
Acc't. No. CS53-58250-810360-00-53W0323                 $17,846.13
Title
Improvements accepted for Mineral Point Rd. @ Junction Rd. - Right Turn Lane, Contract No. 5966.  (9th AD)
Body
BE IT RESOLVED, that the street improvements on Mineral Point Rd. @ Junction Rd. - Right Turn Lane have been completed on 9/21/06  be and are hereby accepted.  
 
Original Contract Sum      $            90,269.00
(Based on Actual Units)      $            96,966.56
Net Change by Change Orders      $            17,846.13.00 or 19.76%
Liquidated Damages      $                    0.00
Final Contract Amount      $          114,812.69