Madison, WI Header
File #: 83678    Version: 1 Name: Awarding Public Works Contract No. 9358, Bartillon Shelter (District 12) and amending the 2024 Adopted Capital and Operating Budgets of the Community Development Division to provide funding needed to complete the project.
Type: Resolution Status: Report of Officer
File created: 5/29/2024 In control: Engineering Division
On agenda: 6/18/2024 Final action:
Enactment date: Enactment #:
Title: Awarding Public Works Contract No. 9358, Bartillon Shelter (District 12) and amending the 2024 Adopted Capital and Operating Budgets of the Community Development Division to provide funding needed to complete the project. (District 12)
Sponsors: Satya V. Rhodes-Conway, Yannette Figueroa Cole, Amani Latimer Burris, Tag Evers, Marsha A. Rummel
Attachments: 1. 9358.pdf, 2. 9358 award.pdf
Fiscal Note
The proposed resolution authorizes the award of Public Works Contract No. 9358, Bartillon Shelter and amends the 2024 Adopted Capital and Operating Budgets of the Community Development Division. The budget amendment transfers $2,000,000 of existing American Rescue Plan Act (ARPA) funding from the youth-focused affordable housing development project at 1202 S. Park Street (Munis 13776) to the Bartillon Shelter project (Munis 13346). In its place, the resolution authorizes up to $2,000,000 of Federal Emergency Rental Assistance Housing funds, that are available in the 2024 CDD Adopted Operating Budget, and currently uncommitted, to support the 1202 S. Park Street development.

The proposed resolution authorizes the award of the base bid and alternates 1, 2 and 3 in Public Works Contract No. 9358. The budget amendment provides sufficient additional budget authority to award Public Works Contract No. 9358 - Bartillon Shelter and complete the remaining non-Public Works project costs (i.e. design consultant fees, staff time, furnishings/fixtures/equipment, percent for art, and related startup costs) while maintaining City support for the proposed youth-focused affordable housing development to be built at 1202 S. Park Street. No net fiscal impact on the City’s budget.
Title
Awarding Public Works Contract No. 9358, Bartillon Shelter (District 12) and amending the 2024 Adopted Capital and Operating Budgets of the Community Development Division to provide funding needed to complete the project. (District 12)
Body
WHEREAS, the Common Council has approved the development of the first purpose-built homeless shelter in Madison, intended primarily to serve persons who identify as male and who experience homelessness, and has authorized the use of approximately $25,000,000 of combined City, County and Federal resources to support the design and construction of that facility; and,

WHEREAS, after the project team charged with leading the City’s effort completed...