Fiscal Note
Funds are available in Acct. No. CT28-58250-822801-00-53B0681 $363,944.69
Title
Improvements Accepted for South Bedford Street Reconstruction Street Assessment District - 2001, Contract No. 5315 (4th AD)
Body
BE IT RESOLVED, that the street improvements on South Bedford Street Reconstruction Street Assessment District - 2001 have been completed on 12/01/02 be and are hereby accepted.
Original Contract Sum $287,540.40
Final Contract Sum
(Based on Actual Units) $316,772.18
Net Change by Change Orders $ 49,172.51 or 17.1%
Liquidated Damages $ 2,000.00
Final Contract Amount $363,944.69