Title
Amending the 2009 Adopted Capital Budget of Engineering-Major Streets and Authorizing the Mayor and City Clerk to enter into an agreement with Foth Infrastructure and Environment for design engineering services for University Avenue from Segoe Road to Shorewood Boulevard. The City has applied for Economic Stimulus Funds for construction. (11th AD)
Body
PREAMBLE
The City is proposing to reconstruct University Avenue from Segoe Road to Shorewood Boulevard. The City of Madison will be the lead agency for this project which also involves Dane County and the Village of Shorewood Hills. The City of Madison has applied for Economic Stimulus Funds for construction. Design will be funded with local funds.
This specific project was not listed in the 2009 Engineering Capital Budget because it was originally scheduled for construction in 2011. If Economic Stimulus Funds are received construction will be advanced to 2010. Funds for design are available in the Engineering Major Streets Capital Budget account number 810571, Major Street Projects.
A purchase order will be issued prior to execution of the agreement with the design consultant in order to proceed as quickly as possible. Projects funded with Economic Stimulus Funds require aggressive design schedules in order to meet the goals and deadlines associated with the funding type.
Pursuant to City Ordinances and Policies, the City Engineer advertised for consultant proposals, reviewed the submitted proposals, and recommends the design engineering contract be awarded to Foth Infrastructure and Environment.
NOW THEREFORE BE IT RESOLVED that the Mayor and City Clerk are hereby authorized to execute an agreement with Foth Infrastructure and Environment for design engineering services for University Avenue from Segoe Road to Shorewood Boulevard.
BE IT FURTHER RESOLVED that the Mayor and City Clerk are hereby authorized to execute agreements with Dane County and the Village of Shorewood Hills for cost sharing for the design of University Avenue from Segoe Road to Shorewood Boulevard.
BE IT FURTHER RESOLVED that the City Purchasing Agent is authorized to issue a Purchase Order in the amount of $25,000 to Foth Infrastructure and Environment for design services.
BE IT FURTHER RESOLVED that the 2009 Capital Budget for Engineering -Major Streets be amended as follows:
University Avenue: Segoe to Shorewood, Project Number 53, Account No. 810358
CS53-58250-810358 $352,000 (Street Construction)
CS53-79140-810358 ($352,000) (GO proceeds)
CS53-79140-810571 $352,000
CS53-58250-810571 ($352,000)
Fiscal Note
The budget amendment contained in this Resolution increases the budget authority in the University Ave: Segoe to Shorewood (project 53) of the 2009 Engineering Major Streets Capital Budget. This budget amendment will be funded through a transfer of GO Borrowing authority from 810571.
Estimated Cost $ 352,000
Acct. No. CS53-58250-810358-00-53W0751