File #: 47705    Version: 1 Name: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on CTH M between Cross Country Road to Prairie Hill Road.
Type: Resolution Status: Passed
File created: 6/14/2017 In control: BOARD OF PUBLIC WORKS
On agenda: 7/11/2017 Final action: 7/11/2017
Enactment date: 7/18/2017 Enactment #: RES-17-00548
Title: Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on CTH M between Cross Country Road to Prairie Hill Road.
Sponsors: Paul E. Skidmore
Attachments: 1. Noise Letter CTH M.pdf

Fiscal Note

No funds required.

Title

Approving temporary construction work with associated noise impacts between the hours of 7:00 PM and 7:00 AM on CTH M between Cross Country Road to Prairie Hill Road.

Body

 

PREAMBLE

 

 

 

The Wisconsin Department of Transportation plans reconstruct the roadway to an urban roadway with four (4) to six (6) vehicular travel lanes, two (2) on-road bike lanes, curb and gutter, sidewalk, multi-use path, street lighting, and a curbed, grassed median. The Project is planned for construction in the year 2017-19.

 

The work of this project cannot be constructed between the hours of 7:00 AM and 7:00 PM because:

 

1.                     Intersection work and utility installation across the roadway must be completed at night to minimize the amount of disruption to normal daily traffic and increases the likelihood of completing the project within the expedited schedule allowed.

 

The proposed activities beyond the hours of 7:00 AM to 7:00 PM are as follows:

 

1.  Intersection work and public utility (sanitary sewer, water main, storm sewer) installation across the roadway.

 

2.  Private utility installation across the roadway by MG&E.

 

The estimated Dates are as follows:

 

1.   Intersection work and public utility (sanitary sewer, water main, storm sewer) installation - 10 nights throughout construction.

 

2.  Private utility installation - 9 nights throughout construction, July 1, 2017 - October 31, 2017.

These date ranges are approximate, and will be more clearly defined as the work areas are identified or as weather and unforeseen circumstances dictate.

 

Construction activities generally exceed the noise limits imposed by the Madison General Ordinances and temporary construction activity between the hours of 7:00 AM to 7:00 PM is allowed to exceed the noise limits imposed by the Madison General Ordinances section 24.08 (3) provided the Common Council adopts a resolution allowing the construction. 

 

NOW THEREFORE BE IT RESOLVED, that construction work, with associated noise impacts, between the hours of 7:00 PM and 7:00 AM on CTH M between Cross Country Road to Prairie Hill Road are hereby approved in accordance with section 24.08(3) of the Madison General Ordinances, and

 

BE IT FURTHER RESOLVED, that the construction activities outside of the hours of 7:00 AM to 7:00 PM are limited to those activities identified in this resolution and are limited to the hours specified, and

 

BE IT FURTHER RESOLVED, that the approval of that construction work, as provided in this resolution shall expire on December 31, 2019.