Madison, WI Header
File #: 00274    Version: 1 Name: Authorizing the Mayor and the City Clerk to execute agreements with the State of Wisconsin Department of Transportation for the design and construction for the East Johnson Street Pedestrian Underpass, and amending the 2004 Capital Budget for Bikeways.
Type: Resolution Status: Passed
File created: 1/13/2005 In control: BOARD OF PUBLIC WORKS
On agenda: 1/18/2005 Final action: 1/18/2005
Enactment date: 1/31/2005 Enactment #: RES-05-00083
Title: Authorizing the Mayor and the City Clerk to execute agreements with the State of Wisconsin Department of Transportation for the design and construction for the East Johnson Street Pedestrian Underpass, and amending the 2004 Capital Budget for Bikeways. Various Ald. Districts.
Sponsors: Common Council By Request

Fiscal Note

Funds Available in the Following  Accounts:

 

Design and Path Construction CS53-58240-810375-00-53B0754; Sanitary Sewer Design: ES01-58275-810332-00-53B0754: Water Main Design: EW01-58273-810455-00-53B0754;

Storm Sewer: ESTM-58270-810381-00-53B0754;

Lighting: CS53-58545-810375-00-53B0754;

Street: CS53-58250-810375-00-53B0754

Sanitary Sewer: ES01-58275-810332-00-53B0754;

Water Main: EW01-58273-810455-00-53B0754

Easements: CS53-58130-810375-00-53B0754

 

Estimated Cost shown below:

 

 

TOTAL EST. COST

FEDERAL / STATE  SHARE

CITY SHARE

PEVIOUSLY ENCUMBERED

CITY COST TO BE  ENCUMBERED

Design (Participating)

$195,000

$ 156,000

$ 39,000

$ 39,000

$   0

Design (Sanitary Sewer)

$ 3,000

$ 0

$  3,000

$  3,000

$   0

Design (Water Main)

$ 5,000

$ 0

$  5,000

$  5,000

$   0

Path (inc. bridge) Constr.

$320,000

$256,000

$ 64,000

$  0

$ 64,000

Storm Sewer Construction

$192,500

$150,000

$ 42,500

$  0

$ 42,500

Lighting and  Electrical

$ 38,500

$30,000

$  8,500

$  0

$  8,500

Street Construction

$435,000

$ 128,000

$307,000

$  0

$307,000

Sanitary Sewer Constr.

$129,000

$   0

$129,000

$  0

$129,000

Water Main Construction

$ 87,000

$  0

$ 87,000

$  0

$ 87,000

Easements

$  5,000

$  0

$  5,000

$2,800

$  2,200

Totals

$1,410,000

$720,000

$690,000

$49,800.00

$640,200.00

 

Note: The City of Madison has executed a three-party agreement with Wisconsin Department of Transportation and MSA Professional Services for design of the project, which has caused funds to be encumbered.  The purpose of this agreement is to secure Federal and State funding for the project and to allow the City to pay those costs not covered by federal funding.  All costs except for Sanitary Sewer, Water Main and Easements are eligible for 80% federal participation.  However, federal funds under the Enhancement Program are capped at $720,000 for this  project and are expected to  cover approximately 50% of project costs. 

 

Title

Authorizing the Mayor and the City Clerk to execute agreements with the State of Wisconsin Department of Transportation for the design and construction for the East Johnson Street Pedestrian Underpass, and amending the 2004 Capital Budget for Bikeways. Various Ald. Districts.

Body

PREAMBLE

 

The City is proposing to construct a shared use path and underpass of East Johnson Street at the Yahara River, which will provide a safe crossing for bicycles and pedestrians.  This project is a component of the Yahara River Parkway Master Plan, approved by the City in 1998.  The project has been approved for federal funding covering  80%  of the cost of design and construction, excluding sanitary sewer, water main and real estate, to a maximum cap of  $720,000.00.  The remaining costs will be funded by the City of Madison. 

 

This resolution increases the authorization for the 2004 Capital Budget of Bikeways in the Engineering - Other  Budget by $270,000.  The funding for this increase came from remaining funds in High Crossing Boulevard (810078) $100,000 and Sidewalks (810068) $170,000.

 

A previous Resolution (No. 60041, ID 33083) was adopted January 7, 2003 authorizing an agreement with Wisconsin Department of Transportation for the design phase of this project. The current resolution authorizes a revised agreement which includes design as well as construction costs, and supersedes the previous agreement.

 

NOW THEREFORE BE IT RESOLVED  that the Mayor and City Clerk are hereby authorized to execute an agreement with the State of Wisconsin Department of Transportation for the design and construction of the East Johnson Pedestrian Underpass  at the Yahara River.

 

BE IT FURTHER RESOLVED, that the Comptroller be authorized to transfer available funds from High Crossing Boulevard (810078) in the amount of $100,000 and from Sidewalks (810068) in the amount of $170,000 to Bikeways (810375) to fund a portion of the cost of this project .