File #: 05970    Version: 1 Name: Approving the geometric design for converting Winnebago St to two-way traffic at Williamson St to allow direct access into the Schenk Atwood business district, & a final determination of the geometric design for First St between Winnebago St & Eastwood Dr
Type: Resolution Status: Filed
File created: 3/15/2007 In control: PEDESTRIAN/BICYCLE/MOTOR VEHICLE COMMISSION (ended 6/2018)
On agenda: 3/27/2007 Final action: 10/13/2010
Enactment date: Enactment #:
Title: Approving the geometric design for converting Winnebago Street to two-way traffic at Williamson Street to allow direct access into the Schenk Atwood business district, and a final determination of the geometric design for First Street between Winnebago Street and Eastwood Drive. (6th AD)
Sponsors: Judy K. Olson
Attachments: 1. Winnebago_Twp_Way_Plan1A_041807.pdf
Fiscal Note
No funds required.
Title
Approving the geometric design for converting Winnebago Street to two-way traffic at Williamson Street to allow direct access into the Schenk Atwood business district, and a final determination of the geometric design for First Street between Winnebago Street and Eastwood Drive. (6th AD)
Body
PREAMBLE
 
The Council-adopted Schenk-Atwood Neighborhood Business District Master Plan, dated 12/7/2000, recommends that Winnebago Street be converted to two-way traffic at Williamson Street to allow direct access into the Schenk Atwood business district while maintaining a choice to bypass the business district on Eastwood Drive.  Figure 15 (page 43-44) of the Master Plan illustrates the proposal.  The Neighborhood Plan "recommends that the historic traffic patterns and the relationship of Schenk's Corners to the arterial street system be re-established while continuing to allow commuters to bypass the district on Eastwood Drive and First Street."  In addition to de-isolating the business district and providing better, more
direct access and way-finding, the proposal would directly support the Neighborhood and Master Plan goals of revitalizing and promoting strong neighborhood centers and businesses.  A separate but related Plan recommendation is to reconstruct First Street south of Winnebago Street for one-way traffic flow into Eastwood Drive.
 
A number of neighborhood meetings have been held over the last several years to review and discuss concepts and plans for implementing the Plan recommendation of a Winnebago Street two-way at Williamson Street. The last major neighborhood meeting was held May 9, 2006, where the Neighborhood Plan proposal was further developed into a preliminary
geometric design drawing, referred to as Option 1.  Since that meeting, additional information has been gathered and funds have been included in the 2007 Capital Budget.
 
Merry Street and Buell Street have been scheduled for reconstruction in 2008.  The design of the intersections of those streets and Winnebago Street would be facilitated with the adoption of a plan for Winnebago Street.
 
NOW THEREFORE BE IT RESOLVED Winnebago Street be converted to two-way traffic at Williamson Street to allow direct access into the Schenk Atwood business district as recommended in the Council-adopted Schenk-Atwood Neighborhood Business District Master Plan, dated 12/7/2000; and
 
BE IT FURTHER RESOLVED that the geometric design for this conversion is approved as shown in the  geometric design drawing, referred to as Option 1; and
 
BE IT FINALLY RESOLVED that the City Engineer and City Traffic Engineer are directed to hold a neighborhood meeting regarding the geometric design prior to action by the Board of Public Works and Common Council.