File #: 94626    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Village at Autumn Lake Phase 15, Private Contract No. 9378 (District 17).
Type: Resolution Status: Passed
File created: 9/2/2026 In control: Engineering Division
On agenda: 9/22/2026 Final action: 9/22/2026
Enactment date: 9/25/2026 Enactment #: RES-26-00501
Title: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Village at Autumn Lake Phase 15, Private Contract No. 9378 (District 17).
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 9378 Street Schedule A excluding bituminous.pdf, 2. VAL Ph 15 Sanitary Schedule A Unit Cost.pdf, 3. VAL Ph 15 Storm Schedule A Unit Cost.pdf

Fiscal Note

No City funds required. Private contract.

Title

Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In Village at Autumn Lake Phase 15, Private Contract No. 9378 (District 17).

Body

WHEREAS, VAL, LLC, has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in:  Village at Autumn Lake Phase 15.

 

NOW, THEREFORE, BE IT RESOLVED

 

1.  That said sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) be and are hereby accepted. 

 

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service". 

 

SANITARY SEWER ACCOUNTING DATA

 

A)                     Total Contract Value (including Engineering

                     and Miscellaneous Costs)                                                               $                     251,110.72                     

 

B)                     Contributions in Aid of Construction:

                     a)                     Public Sewer Components                                          $                     251,110.72                     

                     b)                     Sewer Laterals                                                               $                     ____-0-                     

 

C)                     Investments in Capital (MSU Share)                     $                     ____-0-                     

 

D)                     Total Plant Value                                                                                    $                     251,110.72                     

 

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service". 

 

Increase in Total Plant Value per Schedule “A”                     $454,169.60.

 

4. That the street improvements, excluding the bituminous pavement, on the following streets be and are hereby accepted:

 

•                     Woodbine Drive from Felland Road to August Moon Drive

•                     Woodbine Drive from August Moon Drive to East Property Line of Lot 1452

•                     August Moon Drive from Woodbine Drive to Clover Basin Lane

•                     August Moon Drive from Clover Basin Lane to North Property Line of Lot 1433

•                     Clover Basin Lane from August Moon Drive to East Property Line of Lot 1426

•                     East Side Felland Road Sidewalk from Woodbine Drive to S of Tranquility Trail

•                     East Side Felland Road Sidewalk from S of Tranquility Trail to Tranquility Trail

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 14929 by $ 359,098.44 for a useful life of 40 years.