File #: 78676    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/30/2023 In control: Parks Division
On agenda: 7/25/2023 Final action: 7/25/2023
Enactment date: 7/28/2023 Enactment #: RES-23-00512
Title: Amending the 2023 Adopted Parks Division Capital Budget to transfer $680,565 of existing budget authority and $60,000 of additional Park Impact Fee support to the Door Creek Park Shelter Project. (District 16)
Sponsors: Yannette Figueroa Cole, Jael Currie
Attachments: 1. Door Creek Park Shelter Bid.pdf

Fiscal Note

The proposed resolution amends the 2023 Parks Capital Budget by authorizing a net-neutral transfer of $680,565 in existing GO borrowing authority between major projects and an additional $60,000 in Park Impact Fee support for the Door Creek Park Shelter Project (Munis #14334). The Door Creek Park Shelter Project does not have sufficient funding to cover the award for Public Works Contract No. 9326. The available budget authority in Munis #14334 is $3,200,000 and the contract total is $3,780,498 (including contingency). The project also requires a new fiber connection to the building, estimated at $155,000, for a project total of $3,935,497. The combined existing project authority, proposed GO transfers and impact fee support total $3,940,565. No additional appropriation is required.

 

The GO borrowing transfers are from multiple projects with unused appropriation authority, including:

 

Amount

Project Name

Munis

$            159,000

Reindahl Restroom

10564

 $              25,000

 Olbrich Cistern

10564

 $              33,787

Tenney Acoustics

17443

 $              31,703

Hoyt/Peace Park

17421

 $              46,613

2021 Shoreline Improvements

10605

 $              18,870

Odana School Drainage

17433

 $              80,316

Summit Repaving

17443

 $              45,120

Hillcreek Park Improvements

17233

 $            100,001

Yahara Storage

17443

 $              40,155

Northeast Park

17234

 $            100,000

 PV installation

10562

 

 

Title

Amending the 2023 Adopted Parks Division Capital Budget to transfer $680,565 of existing budget authority and $60,000 of additional Park Impact Fee support to the Door Creek Park Shelter Project. (District 16)

Body

WHEREAS, the adopted park master plan identifies a new multi-season, reservable shelter building in Door Creek Park; and,

 

WHEREAS, the 2020 Capital Budget included funding for architectural, engineering, bidding, and construction administration consultant services; and,

 

WHEREAS, Aro Eberle Architects was selected through a “Request for Proposal” in accordance with MGO Section 4.26 of Madison General Ordinances; and,

 

WHEREAS, the City of Madison and Aro Eberle Architects entered into a contract for professional architectural design services for the Door Creek Park Shelter project on May 13, 2020 (RES-20-00242, File ID 59941); and,

 

WHEREAS, Madison Parks, City Engineering, and the project consultant team conducted community outreach and engagement for the design of the new building; and,

 

WHEREAS, the proposed building will provide year-round, indoor, conditioned, reservable community space, and enhanced public restrooms in Door Creek Park; and,

 

WHEREAS, the Common Council authorized the Board of Public Works to advertise and receive bids for the Door Creek Park Shelter (RES-23-00036, Leg File 75279); and

 

WHEREAS, the construction project was let for Public Works Bidding on February 2, 2023; and

 

WHEREAS, and zero bids were received on April 20, 2023, and

 

WHEREAS, the construction project was let a second time for Public Works Bidding on May 12, 2023; and

 

WHEREAS, three bids were received on June 22, and additional funds are necessary to award the Public Works contract and complete the project to close out; and

 

WHEREAS, no increase in general fund supported General Obligation borrowing is required to transfer existing budget authority to the Door Creek Park Shelter project; and

 

WHEREAS, the amendment provides sufficient funding through construction completion and project close out; and

 

NOW, THEREFORE, BE IT RESOLVED that the 2023 Adopted Parks Division Capital Budget is amended to transfer $680,565 of existing budget authority and $60,000 of additional Park Impact Fee support to the Door Creek Park Shelter Project.