Madison, WI Header
File #: 25669    Version: Name: AMENDED SUBSTITUTE - Accepting the report by Strand Associates - East Johnson Traffic Study and maintain the one way pair street system of East Johnson Street and East Gorham Street and authorizing City Engineering and City Traffic Engineering to proceed
Type: Resolution Status: Passed
File created: 3/14/2012 In control: BOARD OF PUBLIC WORKS
On agenda: 5/15/2012 Final action: 5/15/2012
Enactment date: 5/18/2012 Enactment #: RES-12-00405
Title: AMENDED SUBSTITUTE - Accepting the report by Strand Associates - East Johnson Traffic Study and maintain the one way pair street system of East Johnson Street and East Gorham Street and authorizing City Engineering and City Traffic Engineering to proceed with a design for reconstruction of East Johnson Street with one-way traffic. (2nd AD)
Sponsors: Bridget R. Maniaci
Attachments: 1. Version 1 25669.pdf, 2. East Johnson Street Traffic Study Report.pdf, 3. East Johnson Street Traffic Study Appendices.pdf, 4. BID comments to PBMVC on Johnson St study.pdf, 5. DMI Johnson-Gorham.pdf, 6. 04_18_12 Klebba Letter to EDC.pdf, 7. TLNA.pdf, 8. mayor email - johnson & gorham.pdf, 9. Comments 042312.pdf, 10. Registrants E.2..pdf, 11. Registration Forms Common Council Meeting 5-15-12.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
5/15/20122 COMMON COUNCIL Adopt the Following Amendment(s)Fail Action details Meeting details Not available
5/15/20122 COMMON COUNCIL Adopt SubstitutePass Action details Meeting details Not available
5/2/20122 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT - REPORT OF OFFICERPass Action details Meeting details Not available
4/24/20122 PEDESTRIAN/BICYCLE/MOTOR VEHICLE COMMISSION (ended 6/2018) Return to Lead with the Recommendation for ApprovalPass Action details Meeting details Not available
4/23/20121 PLAN COMMISSION Return to Lead with the Recommendation for ApprovalPass Action details Meeting details Not available
4/19/20121 LONG RANGE TRANSPORTATION PLANNING COMMITTEE (ended 6/2018) Return to Lead with the Recommendation for ApprovalPass Action details Meeting details Not available
4/18/20121 ECONOMIC DEVELOPMENT COMMITTEE Return to Lead with the Following Recommendation(s)Pass Action details Meeting details Not available
3/27/20121 PEDESTRIAN/BICYCLE/MOTOR VEHICLE COMMISSION (ended 6/2018) ReferPass Action details Meeting details Not available
3/21/20121 BOARD OF PUBLIC WORKS Refer  Action details Meeting details Not available
3/21/20121 BOARD OF PUBLIC WORKS Refer  Action details Meeting details Not available
3/21/20121 BOARD OF PUBLIC WORKS Refer  Action details Meeting details Not available
3/21/20121 BOARD OF PUBLIC WORKS Refer  Action details Meeting details Not available
3/20/20121 COMMON COUNCIL Referred  Action details Meeting details Not available
3/14/20121 Engineering Division Referred for Introduction  Action details Meeting details Not available
Fiscal Note
No funds required
Title
AMENDED SUBSTITUTE - Accepting the report by Strand Associates - East Johnson Traffic Study and maintain the one way pair street system of East Johnson Street and East Gorham Street and authorizing City Engineering and City Traffic Engineering to proceed with a design for reconstruction of East Johnson Street with one-way traffic. (2nd AD)
 
Body
The City is proposing to reconstruct East Johnson Street from North Butler Street to North Baldwin Street in 2014.  The city retained Strand & Associates to study the effects of changing East Johnson & East Gorham Streets to two way streets.   The consultant's services included modifying the regional model to identify alternate routes, and model specific intersections determine the affects of the traffic diversions.
 
The study included analysis on four different design scenarios.  
1.  Maintain One-Way Operation
2.  Full Two-way Conversion from Wisconsin Avenue to Baldwin Street.
3.  Two-Way operation east of Blair Street with peak hour parking restrictions inbound and outbound on East Johnson Street
4.  Two-Way operation east of Blair Street with peak hour parking restrictions inbound on East Gorham Street and outbound on East Johnson Street.
 
An online survey and two public information meetings were held to obtain public input.
 
The four design scenarios were analyzed using travel demand modeling and traffic operations modeling.  The scenarios were compared/analyzed with respect to:
 
1.  Bike Conditions
2.  Pedestrian Crossings
3.  Transit
4.  Parking
5.  Business Accessibility
6.  Maintain Trees
7.  Improve Aesthetics
8.  Motor Vehicle Operations / Congestion
9.  Traffic Diversion
10.  Safety
11.  Cost
 
Based upon the findings of the study, the study team recommends scenario 1 (Maintain One-Way Operation) should be moved forward into design as it best balances the multiple goals that have been identified as most important to a successful 2014 reconstruction project on East Johnson Street.   
 
 
NOW THEREFORE BE IT RESOLVED that the report by Strand Associates - East Johnson Traffic Study are hereby accepted and,
 
BE IT FURTHER RESOLVED that the report and its findings will be further reviewed within the context of the planned City of Madison Transportation Master Plan, and,
 
BE IT FURTHER RESOLVED that City Engineering and City Traffic Engineering are hereby authorized to proceed with a design for reconstruction in 2014 of East Johnson Street between North Butler and North Baldwin Streets as a one-way street with the provision that the design not prevent a conversion to two-way operation in the future.
 
 
BE IT FURTHER RESOLVED that the City shall maintain the one way pair street system of East Johnson Street and East Gorham Street and,
BE IT FURTHER RESOLVED that City Engineering and City Traffic Engineering are hereby authorized to proceed with a design for reconstruction of East Johnson Street with one-way traffic.