00269
Authorizing the City Engineer to purchase 3.acres of wetland credits from Wisconsin 
Waterfowl Association, Incand amend the 2005 Stormwater Utility Capital Budget to 
increase general obligation borrowing by $110,000.
1.
The Board took action on this item at its January 5th meetingFiscal note was changed 
and additional wording was added. (City-Wide AD)
PUBLIC WORKS CONSTRUCTION MANAGEMENT - PRIVATE CONTRACTS
00313
Approving plans and specifications for public improvements necessary for the 
Subdivision known as The American Center Plat Buttonwood Addition   and authorizing 
construction to be undertaken by the Developer, Private Contract No2020
2.
(17th AD)
00314
Approving plans and specifications for public improvements necessary for the 
Subdivision known as Lancaster Drive Certified Survey Map and authorizing 
construction to be undertaken by the Developer, Private Contract No2022 
3.
(17th AD)
00315
Accepting street improvements, excluding the bituminous pavement, constructed by 
private contract in Reston Heights Phase V, Private Contract No1816
4.
(3rd AD)
00316
Accepting sanitary sewer constructed by Private Contract In Reston Heights Phase V,  
Private Contract No1816
5.
(3rd AD)
00317
Accepting storm sewer constructed by private contract in Reston Heights Phase V, 
Private Contract No1816
6.
(3rd AD)
CHANGE ORDERS TO PUBLIC WORKS CONTRACTS
Approval of Change Order Noto Contract No5631, Fenney Court to Hammersley Stone in 
the amount of $8,774.50 with a time extension of 1-day.
7.
Approval of Change Order Noto Contract No5622, Sanitary Sewer Replacements 
w/Resurfacing East, to Capitol Underground in the amount of $6,193.50.
8.