File #: 77196    Version: 1 Name: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In 4103-4119 Portage Road - Di Loreto Avenue Extension, Private Contract No. 2433
Type: Resolution Status: Passed
File created: 4/10/2023 In control: Engineering Division
On agenda: 5/2/2023 Final action: 5/2/2023
Enactment date: 5/8/2023 Enactment #: RES-23-00354
Title: Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In 4103-4119 Portage Road - Di Loreto Avenue Extension, Private Contract No. 2433 (17th AD).
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2433 Portage Rd Storm Schedule A Unit Cost UPDATED Mar2023.pdf, 2. 2433 Portage Rd Sanitary Schedule A Unit Cost UPDATED Mar2023.pdf, 3. 2433 Street Schedule A complete Schedule A.pdf
Fiscal Note
No City Funds required. Private contract.
Title
Accepting sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) constructed by Private Contract In 4103-4119 Portage Road - Di Loreto Avenue Extension, Private Contract No. 2433 (17th AD).
Body
WHEREAS, Hidden Creek Residences, LLC, has satisfactorily completed the installation of sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, in: Eagle Trace - Phase 6.


NOW, THEREFORE, BE IT RESOLVED

1. That said sanitary sewer, storm sewer, and street improvements (excluding bituminous surface pavement) be and are hereby accepted.

2. That said sanitary sewer improvements are hereby assigned to the Madison Sewer Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Sewer Utility's "Utility Plant In Service".

SANITARY SEWER ACCOUNTING DATA

A) Total Contract Value (including Engineering
and Miscellaneous Costs) $ 74,983.22

B) Contributions in Aid of Construction:
a) Public Sewer Components $ 74,983.22
b) Sewer Laterals $ ____-0-

C) Investments in Capital (MSU Share) $ ____-0-

D) Total Plant Value $ 74,983.22

3. That said storm sewer improvements are hereby assigned to the Madison Storm Water Utility for ownership and maintenance and that the attached Schedule "A" representing the actual cost of construction of these improvements shall be reflected in the Madison Storm Water Utility's "Utility Plant In Service".


Increase in Total Plant Value per Schedule “A” $59,719.63



4. That the street improvements, excluding the bituminous pavement, on the following streets be and are hereby accepted:


· Portage Road from 167’ South of Di Loreto Avenue to Di Loreto Avenue
· Portage...