Madison, WI Header
File #: 47793    Version: 1 Name: Accepting bituminous surface pavement constructed by Private Contract in Cardinal Glenn - Phase 7, Private Contract No. 2343.
Type: Resolution Status: Passed
File created: 6/23/2017 In control: BOARD OF PUBLIC WORKS
On agenda: 7/11/2017 Final action: 7/11/2017
Enactment date: 7/18/2017 Enactment #: RES-17-00574
Title: Accepting bituminous surface pavement constructed by Private Contract in Cardinal Glenn - Phase 7, Private Contract No. 2343.
Sponsors: BOARD OF PUBLIC WORKS
Attachments: 1. 2343 Street with bituminous Schedule A.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsWatch
7/11/20171 COMMON COUNCIL Adopt Under Suspension of Rules 2.04, 2.05, 2.24, and 2.25, and Close the Public HearingPass Action details Meeting details Not available
6/28/20171 BOARD OF PUBLIC WORKS RECOMMEND TO COUNCIL TO ADOPT UNDER SUSPENSION OF RULES 2.04, 2.05, 2.24, & 2.25 - REPORT OF OFFICERPass Action details Meeting details Not available
6/23/20171 Engineering Division Refer  Action details Meeting details Not available

Fiscal Note

Private Contract, No City Funds Are Required.

Title

Accepting bituminous surface pavement constructed by Private Contract in Cardinal Glenn - Phase 7, Private Contract No. 2343.

Body

WHEREAS, MREC VH Madison, LLC has satisfactorily completed the installation bituminous surface pavement by private contract, in accordance with the City of Madison Standard Specifications for Public Works Construction, for:  Cardinal Glenn - Phase 7

 

 

NOW, THEREFORE, BE IT RESOLVED

 

 

That the bituminous surface street improvements on the following streets be and are hereby accepted:

 

 

                     Harvest Moon Lane from Vintage Drive (existing street) to the east lot line of Lot 12.

                     Roman Mist Way from the north line of Lot 56 (existing street) to the south line of Lot 13.

                     Outlet 2 (Pine Lawn Parkway Alley) from the north line of Outlet 3 (existing street) to the north line of Lot 26 (existing street).

 

 

The attached Schedule "A" representing the actual cost of construction of these improvements, which shall increase the street infrastructure value for Project No. 53B2343 by $89,261.61 for a useful life of 40 years.