Madison, WI Header
File #: 30856    Version: 1 Name: Change Order No. 2 to Contract No. 6965, MMB Electrical Panel Upgrade, to Joe Daniels Construction Co., Inc. in the amount of $1,338.88 with an additional 45-days.
Type: Miscellaneous Status: Approved
File created: 7/5/2013 In control: BOARD OF PUBLIC WORKS
On agenda: Final action: 7/24/2013
Enactment date: Enactment #:
Title: Change Order No. 2 to Contract No. 6965, MMB Electrical Panel Upgrade, to Joe Daniels Construction Co., Inc. in the amount of $1,338.88 with an additional 45-days.
Attachments: 1. co 2 - 6965.pdf
Title
Change Order No. 2 to Contract No. 6965, MMB Electrical Panel Upgrade, to Joe Daniels Construction Co., Inc. in the amount of $1,338.88 with an additional 45-days.  
Body
See attached.