Madison, WI Header
File #: 25771    Version: 1 Name: Determining a Public Purpose and Necessity and adopting a Relocation Order for the acquisition of land interests required for the reconstruction and maintenance of existing public sanitary sewer and stormwater drainage improvements associated with the N.
Type: Resolution Status: Passed
File created: 3/27/2012 In control: BOARD OF PUBLIC WORKS
On agenda: 5/15/2012 Final action: 5/15/2012
Enactment date: 5/18/2012 Enactment #: RES-12-00351
Title: Determining a Public Purpose and Necessity and adopting a Relocation Order for the acquisition of land interests required for the reconstruction and maintenance of existing public sanitary sewer and stormwater drainage improvements associated with the N. Franklin - N. Blair Street Sanitary Crossover. (2nd AD)
Sponsors: Bridget R. Maniaci
Attachments: 1. 129-133 N Franklin_color.pdf, 2. 130-206 N Blair_color.pdf, 3. Buckdaddy LLC 130 N Blair TLE Legal.pdf, 4. Ji 129 N Franklin TLE Legal.pdf, 5. Martin 133 N Franklin TLE Legal.pdf, 6. Paul 202 N Blair TLE Legal.pdf, 7. Paul 206 N Blair TLE Legal.pdf
Fiscal Note
Real Estate acquisition costs and staff time estimated at $15,000.00 for this project are available in Acct. No. ES01-58110-810503-00-53W1326 (Land Easement - Easement Acquisition).
Title
Determining a Public Purpose and Necessity and adopting a Relocation Order for the acquisition of land interests required for the reconstruction and maintenance of existing public sanitary sewer and stormwater drainage improvements associated with the N. Franklin - N. Blair Street Sanitary Crossover. (2nd AD)
Body

RELOCATION ORDER OF THE CITY OF MADISON, DANE COUNTY, WISCONSIN

PREAMBLE


On April 10, 2012 the City of Madison Common Council is scheduled to approve File No. 25,658 Approving plans and specifications and authorizing the Board of Public Works to advertise and receive bids for N. Franklin - N. Blair Street Sanitary Crossover. (2nd AD); and,

This proposed Public Works project will repair and rehabilitate a failing 10-inch public sanitary sewer main located within a 6-foot wide City of Madison owned right-of-way which serves four adjacent properties. The sanitary main is severely damaged near N. Blair Street. The most damaged section will be repaired and the entire main will be lined. The project will also replace an existing 15-inch public storm sewer main with a new 24-inch main within that same 6-foot wide City of Madison owned right-of-way. The upgraded public storm sewer will alleviate existing flooding problems within the enclosed depression on N. Franklin Street; and,

City Engineering Division has established Engineering Project No. 53W1326 and Office of Real Estate Services Project Nos. 9901 thru 9905 (inclusive) to facilitate the acquisition of required easements to perform the necessary public sanitary sewer and stormwater drainage improvements reconstruction associated with the 53W1326 - N. Franklin - N. Blair Street Sanitary Crossover reconstruction project.

To accomplish the public sanitary sewer and stormwater drainage improvements...