Madison, WI Header
File #: 20874    Version: 1 Name: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (Districts 1 & 7) by the Common Council, Contract No. 6307.
Type: Resolution Status: Passed
File created: 12/22/2010 In control: BOARD OF PUBLIC WORKS
On agenda: 1/18/2011 Final action: 1/18/2011
Enactment date: 1/20/2011 Enactment #: RES-11-00070
Title: Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (Districts 1 & 7) by the Common Council, Contract No. 6307.
Sponsors: BOARD OF PUBLIC WORKS
Fiscal Note
Breakdown of Costs by Account Number:
 
Acc't. No. CS53-54473-810376-00-53W0706      $324,341.46
Acc't. No. CS53-58280-810376-00-53W0706         $1,370.40
Title
Improvements accepted for Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (Districts 1 & 7) by the Common Council, Contract No. 6307.
Body
BE IT RESOLVED, that the improvements on Annual Construction & Reconstruction of Concrete Sidewalk & Incidental Concrete Curb & Gutter Work Ordered (Districts 1 & 7) by the Common Council have been completed on 10/20/09 be and are hereby accepted.  
 
Original Contract Sum      $           264,767.50
(Based on Actual Units)      $           283,818.00
Net Change by Change Orders      $                   41 893.86 or 15.82%
Liquidated Damages      $                     0.00
Final Contract Amount      $           325,711.86