Fiscal Note
Breakdown of Costs by Account Numbers CP60-58440-910092-00-6092051-60477N02 and CL60-58220-810098-00-6098046-60400C03
Title
Improvements Accepted for Garner Shelter Repairs, Contract No. 5435. (19th AD)
Body
BE IT RESOLVED, That the Garner Shelter Repairs at Garner Park, 333 South Rosa Road, have been completed on September 27, 2005 be and are hereby accepted.
Original Contract Sum $ 86,400.00
(Based on Actual Units)
Net Change by Change Orders $ 18,738.56
Liquidated Damages
Final Contract Amount $105,138.56